California data center generator exemptions
California Energy Commission backup-generation exemptions for data centers: applicant, docket, MW basis and decision date, linked to the CEC order or notice.
10 records in this collection. Source checks: 2026-11-11. Scope and definitions.
| AVAIO — Pittsburg | Pittsburg1 | CA1 | Generator exemption1 | Exempted1 | 921 | Backup generation1 | — | 2025-12-083 | — | 2026-11-11 |
|---|---|---|---|---|---|---|---|---|---|---|
| Digital Realty — Lafayette | Santa Clara1 | CA1 | Generator exemption1 | Exempted1 | 99.81 | Backup generation1 | — | 2023-11-084 | — | 2026-11-11 |
| Equinix — Great Oaks South | San José1 | CA1 | Generator exemption1 | Exempted2 | 991 | Backup generation1 | — | 2021-12-082 | — | 2026-11-11 |
| GI Partners — Bowers | Santa Clara1 | CA1 | Generator exemption1 | Exempted1 | 721 | Backup generation1 | — | 2023-11-083 | — | 2026-11-11 |
| GIC — NorthTown | San José1 | CA1 | Generator exemption1 | Under review1 | 97.31 | Backup generation1 | — | 2025-06-303 | — | 2026-11-11 |
| GIC — Vernon | Vernon1 | CA1 | Generator exemption1 | Under review1 | 991 | Backup generation1 | — | 2026-08-053 | — | 2026-11-11 |
| Martin Avenue — backup generation | Santa Clara1 | CA1 | Generator exemption1 | Exempted1 | 961 | Backup generation1 | — | 2024-06-123 | — | 2026-11-11 |
| Microsoft — San Jose | San José1 | CA1 | Generator exemption1 | Exempted1 | 991 | Maximum facility demand1 | — | 2019-11-151 | 2022-05-261 | 2026-11-11 |
| Microsoft — San José 04 | San José1 | CA1 | Generator exemption1 | Under review1 | 97.81 | Maximum facility demand1 | — | 2023-02-093 | — | 2026-11-11 |
| STACK — SVY03A | Hayward1 | CA1 | Generator exemption1 | Exempted1 | 76.61 | Backup generation1 | — | 2025-05-083 | — | 2026-11-11 |