Data center permits, rezonings and planning decisions

Data center rezonings, permits, appeals, incentive votes and hearings, each with the deciding body, decision date, acreage or MW, and the source document.

43 records in this collection. Source checks: 2026-11-11. Scope and definitions.

Abbots Langley — recovered planning appealAbbots Langley, England1—Planning appeal1Approved1———2025-05-121—2026-11-11
Amazon — BWI-150 to BWI-153Frederick County1MD1Air permit1Permit issued1———2026-03-251—2026-11-11
Amazon — Warrenton special use permitWarrenton1VA1Special-use permit1Approved1——41.70512023-02-141—2026-11-11
Art Data Centres — Ennis judicial reviewCounty Clare1—Court decision1Challenge dismissed12001Reported campus capacity114512025-03-211—2026-11-11
AWS — St. Joseph County tax abatementSt. Joseph County1IN1Incentive decision1Approved1———2024-08-131—2026-11-11
AWS — Stevensburg land rezoningCulpeper County1VA1Rezoning1Approved1——24312022-04-052—2026-11-11
AWS — Vicksburg state incentive extensionWarren County1MS1Incentive decision1Announced1———2025-11-201—2026-11-11
Balloonist — Red Cedar land rezoningMenomonie1WI1Rezoning1Approved1——32422025-08-043—2026-11-11
Bedford — Ampthill Road NSIP directionCentral Bedfordshire, England1—NSIP direction1Direction issued17201IT capacity1—2026-06-151—2026-11-11
Belmont Innovation Campus — revised applicationLoudoun County1VA1Rezoning1Approved1———2024-04-101—2026-11-11
Beltline — rezoning recommendationFranklin County1MO1Rezoning1Recommended denial1——49012026-04-211—2026-11-11
Dartford — New Barn Road NSIP directionDartford, England1—NSIP direction1Direction issued12402IT capacity2—2026-07-011—2026-11-11
EdgeConneX — Ashville annexation denialAshville2OH1Annexation1Denied1——49012026-02-022—2026-11-11
FAE Clark — Old Elberton Road rezoningAthens-Clarke County1GA1Rezoning1Denied1——23312025-10-071—2026-11-11
Forsyth Technology Campus — zoning voteForsyth1GA1Rezoning1Approved1———2026-02-021—2026-11-11
Francis Harris Lane — San Marcos rezoning denialSan Marcos1TX1Rezoning1Denied2———2026-02-172—2026-11-11
Gateway Digital — rezoning recommendationFranklin County1MO1Rezoning1Recommended approval1——57512026-04-211—2026-11-11
Google — Grange Castle appeal approvalSouth Dublin County1—Planning appeal1Approved2———2026-09-232—2026-11-11
Google — Project LochChesterfield County1VA1Wetlands notice1Notice published1———2026-05-131—2026-11-11
Google / Design — Storey County tax abatementsStorey County1NV1Incentive decision1Approved1———2020-09-161—2026-11-11
Iver — Court Lane recovered appealIver, England1—Planning appeal1Approved1———2024-12-061—2026-11-11
Iver — Woodlands Park recovered appealIver, England1—Planning appeal1Approved1———2025-07-091—2026-11-11
Lakeland Equity — Cleveland permit denialCleveland1OH1Development permit1Denied11501IT capacity13512026-05-141—2026-11-11
Meta / Entergy — resource certificationRichland Parish1LA1Utility certification1Approved settlement1———2025-08-201—2026-11-11
Meta / Laidley — air permit noticeRichland Parish2LA1Air permit notice1Notice published1———2026-06-261—2026-11-11
Microsoft — AVC 22Mecklenburg County1VA1Wetlands notice1Notice published1———2026-06-041—2026-11-11
Microsoft — Mount Pleasant expansion approvalMount Pleasant1WI1Development plan1Approved1———2026-01-261—2026-11-11
MLP Ventures — King of Prussia planning decisionUpper Merion Township1PA1Planning permission1Denied1———2026-08-132—2026-11-11
Monarch — Lyon County land designationLyon County1NV1Land-use plan1Approved11501Proposed phase capacity150512025-12-041—2026-11-11
Nebius — Independence incentive approvalIndependence1MO1Incentive decision1Approved18001Reported campus capacity1—2026-03-022—2026-11-11
Pennhurst — East Vincent denialEast Vincent Township1PA1Planning permission1Denied2———2026-05-212—2026-11-11
Price Road — Chandler data center denialChandler1AZ1Rezoning1Denied1———2025-12-111—2026-11-11
Project Blue — Pima County rezoningPima County1AZ1Rezoning1Approved1——29012025-06-181—2026-11-11
PW Digital Gateway — rezoning court outcomePrince William County1VA1Court decision1Approval voided1———2026-03-312—2026-11-11
QTS — RIC5 expansionHenrico County1VA1Wetlands notice1Notice published1———2026-06-091—2026-11-11
Red Ace — Keyser Road rezoningCulpeper County1VA1Rezoning1Approved1——69.1912024-07-021—2026-11-11
Rock Creek — Fort Worth rezoningFort Worth1TX1Rezoning1Approved1——12012024-09-171—2026-11-11
Stratos — MIDA project-area consentBox Elder County1UT1State siting decision1Approved1———2026-05-041—2026-11-11
Talen Energy — Montour rezoning denialMontour County1PA1Rezoning1Denied1——80012026-02-101—2026-11-11
Tallgrass — Laramie County pre-applicationLaramie County1WY1Pre-application meeting1Meeting recorded1———2025-08-0612025-08-0612026-11-11
Vantage — DUB13 appeal refusalSouth Dublin County2—Planning appeal1Denied2———2025-04-042—2026-11-11
Wapseys Wood — NSIP route directionBuckinghamshire, England1—NSIP direction1Direction issued13002IT capacity2—2026-03-161—2026-11-11
Zeewolde — Trekkersveld IV plan annulmentZeewolde1—Court decision1Approval voided1———2023-09-201—2026-11-11

Continue your review

Browse states

For reuse with full provenance: JSON or CSV.