Georgia data center permits and public decisions

Review Georgia data center decisions, permits and policy records. Compare the recorded action, dates and scope, then follow field-level links to the original sources.

4 records in this collection. Source checks: 2026-11-11. Scope and definitions.

DeKalb County — moratorium extension agendaDeKalb County1GA1Proposed pause1Notice published1————2026-07-0712026-11-11
FAE Clark — Old Elberton Road rezoningAthens-Clarke County1GA1Rezoning1Denied1——23312025-10-071—2026-11-11
Forsyth County — data center standards recommendationForsyth County1GA1Zoning rule1Recommended approval1———2025-01-281—2026-11-11
Forsyth Technology Campus — zoning voteForsyth1GA1Rezoning1Approved1———2026-02-021—2026-11-11

Continue your review

Browse states

For reuse with full provenance: JSON or CSV.